Skip to content

Search Concrete Canvas

Canal Lining | M31 Highway, Hungary

CCX-M® used to line newly constructed water run-off channel

Drag
Before
After
16000
of CCX-M® used for erosion control
4 Months
to install
665
installed per day on average

Solution

To mitigate the issues, a trapezoidal outfall channel was designed to collect runoff and drain it to the Kis-rakos river.

The channel lining was specified as CCT2® (a Type II GCCM in accordance with GCCM Specification Standard ASTM D8364) a few years prior to execution of the project. However, at the time of ordering, CCX®, a new Type II GCCM invented by Concrete Canvas Ltd could be proposed that met all the performance requirements of the design and tender specification. These benefits were enhanced by the wider width of CCX® compared with CCT® resulting in a greater rate of productivity and corresponding cost savings.

CCX-M® insulated from cold weather conditions using plastic sheeting
CCX-M® fully cured

Design & Installation

  • CCX-M® Bulk Rolls specified
  • Channel substrate excavated and compacted
  • Transverse layup
  • Perimeter edges secured in anchor trenches with J-pegs, then backfilled with excavated material
  • Overlaps screwed and sealed
  • Intermediate anchoring with J-pegs
  • Hydration completed using a 2m³ bowser and protected with plastic sheeting in cold curing conditions
Baffles covered in CCX-M®

Summary

In total, the installation was completed over a period of approximately 4 months. Due to the construction programme and earthworks required, CCX-M® installation only took place 2 days per week and 8 hours per day. An average of 7 rolls (665m²) of CCX-M® was laid per day.

Completed Channel

Protect Channels at Scale with CCX-M®

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.