1,700m² of CCH8 installed for a tertiary containment lagoon

1700
of CCH8 used to line the drainage channel
14 Days
to install including the excavation of the lagoon
300
of CC5® was used to provide protection to the outer slopes

Solution

To ensure that the lagoon prevented harmful petrochemicals seeping into the ground a number of lining solutions were considered. CCH8 was chosen as the material to line the lagoon, providing both containment and hard armour protection.

CCH8 overlaps thermally welded by Sean Carr Lining Technologies

Design & Installation

  • CCH8 Bulk Rolls specified
  • Lagoon excavated and graded smooth prior to deployment
  • Transverse and vertical layup
  • Perimeter edges secured in anchor trenches
  • CCH8 overlaps thermally welded using a Leister Twinny thermal welder with triple track setup
  • Thermal weld joints air channel tested for strength and permeability
  • Customised to fit around pipe penetrations and sump areas
  • 300m2 of CC5 provided erosion protection to the outer slopes
  • Hydrated using a combination of hydrant and an IBC
Corner, pipe penetrations and sump accomodated

Summary

The installation was carried out in good weather over a period of 2 working weeks, including the excavation of the lagoon, with a total of 1,700m2 of CCH8 installed by a team of 4.