Channel Lining | Oxagon, Neom, Saudi Arabia

4,200m² of CCX-M® Installed for Erosion Control

4200
of CCX-M installed for erosion control
15 Days
to complete installation with a team of six
280
per day installed (average of 3 rolls)

Design & Installation

  • CCX-M® Bulk Rolls specified
  • Channel excavated and compacted
  • Transverse layup
  • Intermediate anchoring for large structure detailing
  • Perimeter edges secured in anchor trenches
  • Hydration completed at night
Channel diverting pumped water

Summary

The project was a resounding success, with a total of 4,200m² of CCX-M® installed in 15 days, by a team of 6 – installing an average of 3 rolls (280m²) per day.

The clients was extremely pleased with how quickly and easily CCX-M® could be installed in a difficult area and how the project was able to be completed within the agreed timescale and budget. They are now looking to use CCX-M® for future projects.

Completed Installation