Saltar para o conteúdo

Pesquisar tela de concreto

Canal Lining | Central Vancouver Island, Canada

CC used to line a large
diversion channel

Project Overview

In August 2016, over 11,000m2 of Concrete Canvas® (CC) GCCM was installed as a protective liner for a large diversion channel at an underground zinc and copper mine on Central Vancouver Island, Canada. The diversion channel, which conveys clean water from the hillside above to a lower creek, was originally lined with shotcrete but the material had begun to degrade over time. It was recommended that the diversion channel should be enlarged and realigned to effectively handle the high-water volume and velocities.

Previous channel lined with shotcrete
CC8® Bulk Roll deployed transversley
11125
of CC8® used to line a large diversion channel
6 Weeks
to complete installation with a crew of six
Design
using substrate drainage and intermediate anchors to resist hydraulic sheer

Design & Installation

  • CC8® Bulk Rolls specified
  • Trees and vegetation removed, channel profile excavated
  • Gravel sub-drainage layer installed with discharge points into secondary channel
  • Transverse layup
  • Perimeter edges secured in anchor trenches
  • Screwed overlap joints
  • Intermediate anchors installed to resist hydraulic shear
  • Hydrated using a water truck
Ariel view of installation

Summary

The installation took 6 weeks to complete with an average crew size of 6 men and daily temperatures up to 34°C. The client was satisfied with the product and the minimal amount of specialist training or equipment required. In addition to this, the speed of installation meant the project was completed before the heavier precipitation arrived at the mine in early October which may have caused significant project delays.

Downstream view of channel – 8 years later
Ariel view of channel – 8 years later

Discover How Concrete Canvas Can Solve Your Challenge

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.