Lagoon Lining | Kingsbury Oil Terminal, Kingsbury, England
1,700m² of CCH8™ installed for a tertiary containment lagoon
Project Overview
In September 2022, 1,700m2 of CC Hydro™ GCCB was installed to provide containment and hard armour protection for a newly installed tertiary containment lagoon in Kinsgbury, England.
An overflow lagoon was required for the terminal as a number of tanks at the site were only operating at ~60-70% capacity due to secondary containment bunds around the tanks not being at a suitable size to contain a spill if the tanks were at full capacity. A number of options were considered, however, the availability of unused land adjacent to some tanks was chosen to install a new overflow lagoon.
Solution
To ensure that the lagoon prevented harmful petrochemicals seeping into the ground a number of lining solutions were considered. CCH8™ was chosen as the material to line the lagoon, providing both containment and hard armour protection.
Design & Installation
- CCH8™ Bulk Rolls specified
- Lagoon excavated and graded smooth prior to deployment
- Transverse and vertical layup
- Perimeter edges secured in anchor trenches
- CCH8™ overlaps thermally welded using a Leister Twinny thermal welder with triple track setup
- Thermal weld joints air channel tested for strength and permeability
- Customised to fit around pipe penetrations and sump areas
- 300m2 of CC5™ provided erosion protection to the outer slopes
- Hydrated using a combination of hydrant and an IBC
Summary
The installation was carried out in good weather over a period of 2 working weeks, including the excavation of the lagoon, with a total of 1,700m2 of CCH8™ installed by a team of 4.