Aller au contenu

Rechercher une toile en béton

Lagoon Lining | A23, Brighton, UK

Two Attenuation Ponds Lined with CCHT1

Project Overview

In October 2023, CC Hydro GCCB was used to line two attenuation ponds near the A23 north of Brighton, UK. Originally constructed in the early 1990s, the two attenuation ponds were designed to capture runoff water from the A23 and prevent the drainage system becoming overwhelmed in a storm event. Due to the contaminants in this run off it was vital that an impervious surface was installed, a 0.75mm geomembrane with a concrete paving slab cover layer was used in the first instance. Over time, the two attenuation ponds became overgrown with vegetation, with some of the paving slabs becoming dislodged affecting the protective cover to the geomembrane.

Attenuation pond prior to works
Excavators used to remove vegetation
4000
of CCHT1 lined two attenuation ponds
70
of CCHT1 installed per day

Design & Installation

  • Vegetation removed, loose slabs repositioned
  • Geotextile laid to protect CCHT1 geomembrane backing
  • CCHT1 Bulk Rolls specified
  • Perimeter edges secured in anchor trenches
  • Connected to infrastructure using clamping bar and anchors
  • Thermal welded joints air channel tested to verify strength and permeability
  • Pipe boots formed with PVC geomembrane and welded
  • Hydrated after each shift using hose and water
CCHT1 overlapped and thermally welded

Summary

The first pond was completed in 2 weeks with approximately 70m² of CCHT1 installed per day. During the installation of the second attenuation pond, poor weather conditions meant that outlet pipes within the pond had to be bunged. However, these had to be removed every night resulting in the pond filling with water and needing to be drained the following morning. This reduced productivity but enabled the ponds to maintain their function during periods of heavy rainfall.

National Highways were pleased with how the material was installed and the final results. The CC Hydro remediation will provide effective containment and weed suppression, extending the operational life of the ponds.

Outlet pipe covered in CCHT1
Completed Installation

Prevent Seepage with CC Hydro Today

Ce site est enregistré sur wpml.org en tant que site de développement. Passez à un site de production en utilisant la clé remove this banner.