Channel Lining | Church Village Bypass, South Wales, UK
Sustainable Drainage Solution for Church Village Bypass
Project Overview
In February 2010, Concrete Canvas® GCCM (CC) was used to line a drainage channel in Church Village, South Wales. The slope was situated along the crest of a slope, and adjacent to a main road. In the previous year, Costain were appointed as the main contractor for the £90m Church Village Bypass scheme.
Solution
The scheme involved the construction and introduction of two road bridges, four roundabouts, three community footbridges, two cattle grids and one subway, along with the installation of holding ponds and an extensive surface drainage network. The contractor aimed to use alternative materials, such as recycled aggregates, to minimise the impact on the local ecology and environment. Following approval from the Environment Agency, the Costain specified the CC GCCM for use within the drainage network.
CC8™ is a Type II GCCM as defined in ASTM D8364, it is suitable for use on soil subgrades and was chosen for this project to suit the abrasion, wear and loading requirements. CC8™ is also BBA certified with durability in excess of 120 years when used in erosion control applications.
Design & Installation
- CC8™ Bulk Rolls specified
- Vegetation removed and channel reprofiled
- 3 Layer Longitudinal layup
- Screwed Joints
- Perimeter edges secured in anchor trenches
- Hydrated using water bowser and hose
Summary
Berro volum que es eos sinto beaquiasim quidus pro mil illabor simi, totat et, ne la doluptium es atet, oditias re ma dolest aut audae natia era expella sum ut volor rerchil luptati onemoloreri que core cori ad quod quiat ea suntibus sus, voluptatur, siminve rferum qui abo. Nam et et am que est, cone dererum aut ut que et ullorepelis nes dolut quia voluptat experovid moloriam aliquis minulparum archill uptinctiunt labo. Itaeptatur sus.