Channel Lining | La Serena, 4th Region, Chile

Eliminating water losses using Concrete Canvas®

18000
of CC5 used to line channel
40 Days
to install with a team working 9 hour days
2.4km
total length of irrigation channel

Design & Installation

  • CC5 Bulk Rolls specified
  • Channel profile created by over-excavating and then using a portable formwork to compact soil and form the side slopes
  • Transverse layup
  • Perimeter edges secured in anchor trenches
  • Secured to existing concrete with anchors and polyurethane sealant
  • Screwed and sealed overlap joints
CC easily conformed to changes in channel profile

Summary

A total of 18,000m2 of CC5 was installed in 40 days, with the team (of 70 installers working in rotation, with 3 formworks, 11 backhoes and 3 20T excavators utilised) working around 9 hours each day. Due to the way this project was carried out, with multiple smaller teams working at once in stations along the channel, the project was finished on time. As a result of the project’s success, the client has specified CC for another project, and more similar projects with other clients have been specified as a direct result of the Bellavista Channel.