Canal Lining | Alberta, Canada

Irrigation Canal Remediation with CCX-M®

3300
of CCX-M® used to line irrigation canal
1700
installed per day, within 3 days
96%
seepage reduction achieved

Design & Installation

  • CCX-M® Bulk Rolls specified
  • Existing lining removed and channel re-cut
  • Transverse deployment
  • Anchor trenches along perimeter edges
  • Screwed and sealed overlap joints
  • Hydrated using a 2,000-gallon water truck and lay-flat hose
Hydration via a 2,000-gallon water truck & hose

Summary

Offering a minimum operational design life of over 50 years, the lower carbon CCX-M® was installed at less than half the cost and at twice the speed of the concrete alternative using their own crew. Based on the success of this first section, the irrigation district is proposing to line subsequent sections of the North Brudett canal network going forward.

Completed Installation

Transform Your Canal Lining with CCX-M®