Slope Protection | Tutong, Brunei

2,000m² of CC5® installed to provide erosion protection to a steep slope near a large electric pylon

2000
of CC5 used to protect the slope
2 Phase
approach was carried out to line the slope
21 Days
to complete by a team of 10, including climbers

Solution

Bore piles and vegetated erosion control mats were considered for the project, but were disregarded. Bore piles would have been complicated to install due to the limited space and access on the site, particularly as a large pylon sits on top of the slope, just 11m from the edge. Vegetated erosion control mats were disregarded as it was not possible to ensure that vegetation would establish sufficiently to protect the slope. CC was ultimately specified as it would eliminate the requirement for heavy machinery and provide the quickest installation, protecting the entire slope.

The installation conditions were challenging for the ten-person crew. The 31m slope is steep and the soil very hard. As a result, the material had to be deployed from the crest of the slope, with skilled climbers needed to assist in positioning, jointing and fixing the material for health and safety purposes.

Fixing CC to ground using steel pegs

Design & Installation

  • CC5® Bulk Rolls specified
  • Vegetation removed and slope face graded
  • A step was built halfway down the slope to give the excavator safe access to top and bottom sections
  • CC5® Bulk Rolls were deployed vertically down the face of the slope
  • CC5® material was cut and secured within anchor trenches at the crest using steel pegs
  • Due to the hard nature of the substrate, pre-drilling was required before inserting fixings
  • Climbers abseiled down the slope face to adjust positioning of the overlaps
  • Screwed and sealed joint was used
  • Intermediate fixing pegs were used to secure the CC5® to the substrate down the face of the slope
  • CC was hydrated using a portable water tank
Screwing overlapped joints

Summary

The project was carried out in two phases, with the top section of the slope lined first, taking around 14 days. While the second phase saw the bottom section of the slope lined in seven days.

The client was satisfied with the performance of the material in terms of the time required to complete the installation, delivery time, ease of installation and the strength and capabilities of the material.

A total of 2,000m² of CC5® was installed by the team of ten, including climbers, in a total of 21 days.

Completed Installation