Channel Lining | Chipping Warden, England

Sustainable Scour Protection for HS2 Banbury Road Realignment

4400
of CCT2® used to provide erosion protection
12 days
installation by 6 operatives
58%
carbon saving vs poured concrete

Design & Installation

  • 3 Wide-Bulk Rolls of CCT2® specified to reduce number of joints
  • Channel dammed; water pumped to adjacent channel
  • Vegetation removed and profile graded with long-reach excavator
  • Transverse layup
  • Perimeter edges secured in anchor trenches
  • Screwed overlap joints
  • Hydrated using a water bowser and hose
Completed Installation

Summary

Although ground conditions weren’t favourable during installation, the project was completed on schedule with a team of 6 installers installing 4,400m2 of CCT2® at rates of up to 100 linear metres per day.