Bank Erosion Protection | Ras Al Khair, Saudi Arabia

CC5® Installed for Bauxite Liquor Erosion Control

23700
of CC5® used to provide erosion protection
24 Days
to complete installation
41%
carbon saving vs. 100mm poured concrete alternative

Design & Installation

  • CC5® Bulk Rolls specified
  • Slope graded and compacted prior to deployment
  • Vertical layup
  • Perimeter edges secured in anchor trenches
  • Connected to infrastructure using clamping bar and anchors
  • 50mm zigzag overlap joints
  • Hydrated using a water tank and hose with sprinkler head attachment
CC easily accommodates existing infrastructure

Summary

A total of 23,700m² of CC5® material was installed by a local contractor. A team of ten carried out the works over 24 days, with around ten hours worked per day in hot, dry conditions.

The client had provided a very tight deadline for delivery, as they had to make part of the pond operational. The use of CC meant the installation was completed well before the deadline and the project was considered a success.

Completed Installation
A total of 23,700m² of CC5® were installed